Ground Engineering

Marine Parade — CFA Piling & Retaining Wall

Three rows of 600 mm CFA piles and a GCS wall — road corridor ground improvement in Auckland.

Location
Marine Parade, Auckland
Client
Auckland Transport
Designer
Andy O'Sullivan Geotechnical Engineering
Timeline
December 2022 — January 2023
Scope
CFA piling, subsoil drainage and GCS wall

Design

Stabilising the Road Edge

Marine Parade in Auckland, required ground improvement works to remediate an underslip that had reduced the road to one lane. GSI was engaged by Fulton Hogan as a specialist subcontractor, with design by Andy O'Sullivan & Associates.

The works involved undercutting the low-strength slip debris and constructing two counterfort drains and a subsoil drain along the base of the cut batter. Three rows of 600 mm diameter CFA piles were specified to a depth with 1.0 m embedment into the underlying weathered rock, followed by construction of a Geosynthetically Confined Soil (GCS) wall to road level. The CFA piling approach offered a non-disruptive installation method which allowed the road to remain open throughout construction with minimal vibration and noise impact on adjacent properties.

Build

CFA Piling and GCS Wall in Constrained Conditions

Works commenced with road edge excavation and access ramp construction to establish a working platform. CFA columns were then constructed using GSI's FD45 CFA piling rig, spaced at 1.8 m centres and installed at depths between 6.2 m and 11 m depending on the depth to weathered rock. Embedment of 1.0 m into weathered rock was verified by monitoring drilling torque pressure and visually assessing drilling spoil.

The GCS wall was constructed with Cirtex Duramesh facing panels, with AP65 placed in 200 mm compacted layers and Stratagrid SGU80 geogrid repeated at each lift.

Deliver

Road Edge Secured, January 2023

The Marine Parade project was completed in January 2023, delivering a permanent, engineered solution to the road edge instability. The combination of CFA piles and the GCS retaining wall provides long-term structural support with a finished appearance suited to the coastal residential context.

GSI provides specialist CFA piling, ground improvement, and retaining wall construction across Auckland and New Zealand-wide — delivering technically detailed solutions to constrained suburban and coastal sites under single design-build contracts.

600 mm
CFA Pile Diameter
Jan 2023
Completed on Programme
2 Months
Construction Programme

FREQUENTLY ASKED QUESTIONS

Related

Get in Touch

Coastal or Waterfront
Challenge?

Coastal and waterfront geohazard work demands specialist knowledge of tide, wave action, and marine access. Our team has delivered across New Zealand's coastline.

Discuss Your Project

How Can We Help?

No obligation. One of our engineers will be in touch within 24 hours.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.